Milestones

 

Name

Epic/task

Date

Progress

Comment

GDP 11 release GDP-297 - Getting issue details... STATUS week 38In progressBase on the experience gained during the RC1 cycle, the release will most likely take place in week 39 or 40 so there is time to create and deploy the several images required.
GDP 11 RC1 release GDP-335 - Getting issue details... STATUS September 1st 2016(tick)GDP 11 RC1 released.Released For QEMU, Intel Minnowboard, RPI2 and RPi3.
GDP 11 beta release GDP-294 - Getting issue details... STATUS July 28th(tick) Done. Wed Aug 3rdReleased. For QEMU only. Otherwise, please go to GDP Master. The tasks left to do are about tracking the impact of the release.

GDP Roadmap

      GDP-272 - Getting issue details... STATUS         

July 20th

  • Proposal about scenarios sent. Decision about scenario taken. (tick)
  • Roadmap proposal sent and communicated. (tick)
  • Roadmap for GDP 11 beta approved. (tick)
  • Roadmap for GDP 11 RC1 approved. (tick)
  • Roadmap for GDP 11

Roadmap for RC1 release done and communicated. Release plan published.

GDP master

     GDP-231 - Getting issue details... STATUS      

June 10th

(tick)Done: June 22nd

Re-structuring finished. Master has been created and integrated with go.cd. Now GDP has two deliverables, Master and major releases.

Release of Intel Minnowboard

GDP-200

May 18th

(tick)Done: May 18th

GDP-ivi9 port to Intel Minnowboard MAX.

14th AMM Hands on Session

GDP-25

April 27th and 29th

(tick)Done: April 26th and 29th

Hands On Sessions: GDP on Porter and GDP on RPi2. Summary/overview sessions.

GDP-ivi9 release

GDP-36

April 5th

(tick)Done. Tue April 19th

GDP-ivi9 for QEMU, Renesas Porter and RPi2

GDP-ivi9 RC1 release

GDP-35

March 8th 2016

(tick)Done Tue March 8th

GDP-ivi9 RC1 QEMU image

GDP-ivi9 Beta release

GDP-17

Feb 9th 2016

(tick)Done Wed Feb 17th 2016

GDP-ivi9 beta released. Some complementary and analysis tasks are in progress.

Achievements this week

Main achievement on the past week:

 

Name

Epic/task

Date

Comment

GDP 11 RC1 GDP-335 - Getting issue details... STATUS Sept 14thReleased on Sept 1st but the post release tasks completed today.
Master supports Renesas Porter GDP-215 - Getting issue details... STATUS Sept 9thAnnounced through the mailing list.
Master supports Renesas Silk GDP-214 - Getting issue details... STATUS Sept 9thAnnounced through the mailing list.

 

Activity Summary

 

Intensive work on supporting audiomanager 7.4 in GDP, specially rtelated with Audiomanager Monitor. The team has also performed some tests in RPi3 and become familiar with the HMI. GDP 11 RC1 post-release tasks has been completed. Support for Renesas Porter completed and announced.


Description

Main activities

  • GDP Master improvements  
    • Renesas Porter and Silk are supported now in Master  GDP-215 - Getting issue details... STATUS and GDP-214 - Getting issue details... STATUS
      • Announced through the genivi-projects mailing list.
    • Working towards upgrading audiomanager from 7.0 to 7.4 in Master. Issues in different areas like audiomanager monitor  GDP-366 - Getting issue details... STATUS

Other Activities

  • Work to get familiar with HMI HMIL-1 - Getting issue details... STATUS
     
  • Trying to fix encoding problems in qml-example in MAster using a RPI2/3. Issues with Faytech Monitor, not RPi one: GDP-332 - Getting issue details... STATUS
  • Published completed task list for GDP 11 RC1.
  • Tests with RPi3. We have detected performance improvements compared to RPi2
  • Coordination with LRT team to provide them what is required to perform further license checks on GDP 11.
  • Small improvements in Acceptance tests GDP-33 - Getting issue details... STATUS
  • Trying to easy the deployment of Minnowboard images on the board GDP-370 - Getting issue details... STATUS

Issues/Escalations

Unresolved (not discussed last week)

  • We require help from Audio Manager Monitor maintainers to upgrade audiomanager to 7.4 and have sound working.
  • Release date for GDP 11 proposed for Sept 29th. Check the roadmap page and the roadmap document. GDP-272 - Getting issue details... STATUS

Solved (from last week’s report issues)

Next Week Targets

  • Work on Master towards the final release
    •  Update audiomanager to 7.4
    • Provide LRT what is required to perform further license checks.
    • Keep taking small steps in Acceptance testing.